The Cabinet on Thursday approved construction of the second international airport at Navi Mumbai in Maharashtra.
The deadline for the commercial launch of the Navi Mumbai airport is set at 2021-end
The state-run City & Industrial Development Corporation (Cidco), nodal agency for the proposed Navi Mumbai international airport, has asked the New Delhi-based National Institute of Disaster Management (NIDM) to prepare a risk assessment and disaster management plan for the project.
Union ministry of home affairs changed its mind and gave bid clearance for Hiranandani Developers and its consortium partner, Zurich Airport
Former India cricket captain Virat Kohli met Maharashtra Deputy Chief Minister Eknath Shinde in London to discuss enhancing sports infrastructure, athlete development, and the state's progress. The dialogue focused on policy improvements, upcoming sports facilities like a Sports City near Navi Mumbai, and empowering youth through sports initiatives. Kohli also shared his passion for cricket and commitment to guiding young athletes.
Former India cricket captain Virat Kohli met Maharashtra Deputy Chief Minister Eknath Shinde in London to discuss enhancing sports infrastructure, athlete development, and state progress. The meeting focused on policy improvements for sports facilities in Maharashtra and nurturing young talent, with Kohli expressing interest in supporting such initiatives.
An environment impact assessment study by the Indian Institute of Technology, Mumbai, for the proposed Navi Mumbai international airport, has categorically said there should not be any compromise on retaining the geomorphology of rivers, the aquatic life and mangroves in the airport zone.
Offers 12.60% in revenue share to Cidco, while only other bidder GMR offered 10.44%.
Will be operational by the time Mumbai airport reaches its saturation capacity of 40 million.
Actual construction on the Navi Mumbai international airport, which received the much-awaited environment clearances early this week, would begin in October next year as certain formalities remained to be done, said the City and Industrial Development Corporation (Cidco), a nodal agency for the project.
IndiGo is undertaking a comprehensive review of its long-standing policy against fuel hedging, particularly in light of rising jet fuel prices and its ambitious long-haul expansion plans. CEO Willie Walsh stated that while domestic competitors don't hedge, international expansion necessitates a re-evaluation to manage risk and provide stability against volatile fuel costs.
It is clear from the records that the land is in possession of CIDCO for several years.
IndiGo CEO Willie Walsh announced that the airline expects to begin receiving wide-body A350 aircraft from the second quarter of 2028, featuring a three-class configuration, as the airline sees significant opportunities in the long-haul market despite industry challenges like rising fuel costs.
Modi stressed the need to enhance aviation infrastructure capacity to meet the rising demand for air travel.
Under the hybrid-till model, a portion of non-aeronautical revenue (commercial revenue) at the airport is taken into consideration while fixing the landing and parking charges, user fees and other aeronautical charges.
The Maharastra government has given the City and Industrial Develoment Corporation (Cidco) an "in principle" approval to hand over 150 hectares of land for the ambitious project.
GVK Group that runs the swanky MIAL (Mumbai international airport) pipped rival GMR Group to bag the contract for the proposed facility in Navi Mumbai which will ease the severe congestion at the Chhatrapati Shivaji International Airport.
It took 13 years to get environmental clearance for the greenfield international airport at Navi Mumbai.
It is suspected that they caught the infection while on duty at the Mumbai International Airport, the official said.
Adani Airport Holdings (AAHL) has announced it will raise 9,825 crore through a primary equity infusion from a consortium of global investors, including Alpha Wave Global, Premji Invest, Temasek, and funds managed by BlackRock, who will collectively acquire a 5.54 per cent stake.
State-run City and Industrial Development Corporation (Cidco) plans to issue a request for qualification (RFQ) for the Navi Mumbai international airport in the middle of next month.
The project cost was pegged at Rs 4,766 crore (Rs 47.66 billion).
Reconstruction of the terminal is expected to be completed by September 2028.
Officials from the City and Industrial Development Corporation (Cidco) on Thursday expressed fears that the proposed international airport at Navi Mumbai could become unviable due to cost escalation, following prolonged delays.
People affected by the Navi Mumbai international airport insist they be allotted developed land as compensation, not cash as the land acquisition Bill, recently cleared by Parliament
The airport, which will now be built to handle 20 million passengers, will likely start operations by mid-2020. However, rating agency CRISIL in its report in May-end had said operations are expected to start in 2023.
Notwithstanding opposition from some villages to the Rs 14,500-crore (Rs 145 billion) Navi Mumbai airport, the implementing body, Cidco, has decided to go ahead with the project and would issue 'request for qualifications' on February 5.
Strangely, a few days after filing the charges, the CBI teams arrived in Hyderabad and Mumbai to raid GVK's offices and found incriminating evidence, a reversal of the normal course of events.
Maharashtra SEZ act yet to be notified.
Firms are still barred from holding board positions in the special purpose vehicle that will develop the airport.
Despite several rounds of negotiations with villagers, CIDCO is yet to acquire 271 hectares required for the core airport area in Navi Mumbai.
There are four nodes and each of these, like Dronagiri, is also formally termed an SEZ, all part of the NMSEZ.
During the past 30 days, prices of medium residential apartments rose by Rs 300-500 per square feet across various nodes in the city. The present prices range at Rs 2,500-3,000 per square foot across nodes like Kamothe, Panvel, Kharghar, Khandeshwar and CDB Belapur, said Srikanth Puduval, a real estate agent.
If implemented in India, the service will allow passengers book security screening slots in advance, helping cut down wait times in long queues.
The new greenfield airport at Navi Mumbai will come up at the proposed site and not be shifted elsewhere. Maharashtra Chief Minister Vilasrao Deshmukh has also written to the Civil Aviation Ministry for building the airport at the originally proposed site. There had been demands to shift the proposed Navi Mumbai airport to a new site due to environmental issues. The regulator would look into aspects like aeronautical charges, user development fee and passenger fee.
Park Hotels, promoted by Apeejay Surrendra Hotels, has launched the first boutique hotel 'The Park' in Navi Mumbai's CBD Belapur, a thriving business district and a IT-manufacturing hub.
Maharashtra government on Monday offered to provide 22.5 per cent of the developed land to those whose lands would be acquired for the Navi Mumbai International Airport project.
While Smit Machchhar is rightly being lauded as a hero, the curious thing is that the name of the Omani copilot responsible for this attempt to hijack or crash the aircraft has been withheld. His name and face should have been splashed all over the international media. This was not done and it therefore raises legitimate suspicion. Is it possible that his involvement could expose some powerful entity? Could it point to a blatant intelligence failure that would have left certain powers shamefaced? Could it be that he may have revealed things that could prove severely damaging to certain vested interests? asks Vice Admiral Biswajit Dasgupta (retd).
This is the second extension for the bids since June 18.
The CIDCO and the Maharashtra government have stepped up efforts to arrive at a consensus over compensation for PAPs, before a meeting called by the prime minister on November 13 to expedite the work. PAPs, who have dropped their earlier demand of Rs 20 crore (Rs 200 million) per acre, are demanding allocation of 35 per cent developed land against the offer of 22.5 per cent made by the state government and CIDCO.